Completed Projects

Building India's Industrial Future

With India's infrastructure sector driving higher cement demand, the country has emerged as the second-largest producer of quality cement globally. As industry participation continues to expand, Sumit Engineering remains at the forefront of modernization, maintenance, fabrication, erection and technological upgrades for cement manufacturing facilities. With expertise in Boiler Erection and Waste Heat Recovery Systems (WHRS), we help clients maximize operational efficiency, improve plant performance and capitalize on future growth opportunities.
Project Portfolio

Project Execution Portfolio

Sr.Cement PlantJob DetailsTime Period
1Zuari Cement Ltd., Yerraguntla, APInstalled Fly Ash Dryer and BaghouseSep 2009 – May 2010
2JSW Cement Ltd., NandyalFabrication and Erection of PreheaterApr 2010 – Feb 2011
3Zuari Cement Ltd., AttipattuFabrication and Erection of Grinding Unit including Cement Mill, Wagon Tippler, Clinker Silo, Fly Ash System and Packing Plant (3600 TPD)Sep 2010 – Aug 2011
4Zuari Cement Ltd., Yerraguntla, APInstalled Wagon Loading System, Packing Plant, Coal Mill Shed, ESP and associated structuresJan 2011 – Dec 2011
5Bagalkot Cement, KarnatakaFabrication and Erection of Crusher, Baghouse, Preheater, Fly Ash Silo and related equipmentJul 2011 – Sep 2012
6Ultratech Cement Ltd., Birla White, Katni, MPMechanical Fabrication and Erection Works2014
7Zuari Cement, Solapur, MaharashtraFabrication and Erection of Complete Grinding Unit Project (3600 TPD)Feb 2014 – Jan 2015
8Zuari Cement, Cochin, KeralaFabrication and Erection of Complete Grinding Unit ProjectMay 2015 – Feb 2016
9Mangalam Cement, Morak, RajasthanGrinding Unit ProjectMay 2014 – Jul 2014
10Maruti Cement Ltd., Siraha, NepalComplete Plant Project including Crusher, Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Packing PlantMar 2013 – Jan 2015
11Subhashree Agni Cement, NepalComplete Plant Project except Crusher including Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Packing Plant2015 – 2016
12Ultratech Cement Ltd., Vikram Cement Works, Neemuch, MPConversion of Cement Mill Line III ESP to Baghouse2016
13Nuvoco Vistas, Jojobera, JharkhandInstallation of Clinker Slag Roller Press Circuit, Bucket Elevator and Belt Conveyor System2018
14EOM Engineering, Sonadih, ChhattisgarhExpansion of Packing Plant2018
15Subhashree Agni Cement, NepalComplete Project of Cement Grinding Unit2018
16Ultratech Cement Ltd., Shambhupura, RajasthanFabrication and Erection of Belt Conveyor and Calciner Modification Work2019
17Ultratech Cement, Kotputli, RajasthanRaw Mill Cyclone Modification and Height Increase of Cyclone2018
18J K Cement, Mangrol, RajasthanFabrication of Casing, Gas Ducts and Hopper of AQC Boiler and PH Boilers2019
19ACC Gagal, Barmana, Himachal Pradesh under Sinoma LNVTFabrication and Erection of Fly Ash Dryer, Conveyor and Associated Equipment2019 – 2020
20Ambuja Cement, Marwar Mundwa, Rajasthan under Sinoma LNVTFabrication, Copper Slag Blasting and Painting Works (1600 MT)2019 – 2020
21Sagar Cement Group – Satguru Cement Plant, Manawar, MP Fabrication and Erection of Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Complete Plant Equipment. Also executed WHRS Boiler Erection.

Fabrication: 6600 MT | Erection: 14500 MT
2020 – 2021
22Ultratech Cement Ltd., Dhar, Madhya Pradesh – Line II Post Clinkerisation Project Fabrication and Erection of Post Clinkerisation Unit.

Fabrication: 4100 MT | Erection: 7900 MT
2021 – 2022
23ACC Cement, Gagal, Himachal Pradesh Erection of Clinker Silo (Clinker Tank).

Erection: 575 MT
2021
24JK Cement Group – Jaykaycem (Central) Ltd., Panna, MP Fabrication and Erection of Crusher.

Fabrication: 2100 MT | Erection: 4500 MT
2022
25Ultratech Neem Ka Thana Cement Works, Rajasthan Fabrication and Erection of Post Clinkerisation Unit2022
26Ultratech Cement Ltd., Rajpura Cement Works, Punjab Fabrication and Erection of Complete Grinding Unit.

Fabrication: 4400 MT | Erection: 8900 MT
2023 – 2024
27Ultratech Cement Ltd., Kotputli Cement Works, Rajasthan Fabrication and Erection of Post Clinkerisation Unit.

Fabrication: 3400 MT | Erection: 7600 MT
2023 – 2024
28Shree Cement Ltd., Etah Grinding Unit, Uttar Pradesh Successfully completed Fabrication, Erection, Installation and Commissioning within benchmark timelines and received appreciation from Shree Cement Management.2024 – 2025
29Ultratech Cement Ltd., Dalla Cement Works, Uttar Pradesh Complete Pyro Upgradation Shutdown Project involving Fabrication, Dismantling and Erection of Preheater, Coal Mill and Associated Equipment executed successfully within just 40 days, setting a benchmark in the cement industry.2025
30Multiple Cement Plants Across India & Nepal Successful execution of modernization, expansion, shutdown, grinding unit, WHRS and clinkerisation projects across major cement manufacturing facilities.Ongoing Legacy