Sumit Engineering - Header
Completed Projects

Building India's Industrial Future

With India's infrastructure sector driving higher cement demand, the country has emerged as the second-largest producer of quality cement globally. As industry participation continues to expand, Sumit Engineering remains at the forefront of modernization, maintenance, fabrication, erection and technological upgrades for cement manufacturing facilities. With expertise in Boiler Erection and Waste Heat Recovery Systems (WHRS), we help clients maximize operational efficiency, improve plant performance and capitalize on future growth opportunities.
Project Portfolio

Project Execution Portfolio

Sr. Cement Plant Job Details Time Period
1 Zuari Cement Ltd., Yerraguntla, AP Installed Fly Ash Dryer and Baghouse Sep 2009 – May 2010
2 JSW Cement Ltd., Nandyal Fabrication and Erection of Preheater Apr 2010 – Feb 2011
3 Zuari Cement Ltd., Attipattu Fabrication and Erection of Grinding Unit including Cement Mill, Wagon Tippler, Clinker Silo, Fly Ash System and Packing Plant (3600 TPD) Sep 2010 – Aug 2011
4 Zuari Cement Ltd., Yerraguntla, AP Installed Wagon Loading System, Packing Plant, Coal Mill Shed, ESP and associated structures Jan 2011 – Dec 2011
5 Bagalkot Cement, Karnataka Fabrication and Erection of Crusher, Baghouse, Preheater, Fly Ash Silo and related equipment Jul 2011 – Sep 2012
6 Ultratech Cement Ltd., Birla White, Katni, MP Mechanical Fabrication and Erection Works 2014
7 Zuari Cement, Solapur, Maharashtra Fabrication and Erection of Complete Grinding Unit Project (3600 TPD) Feb 2014 – Jan 2015
8 Zuari Cement, Cochin, Kerala Fabrication and Erection of Complete Grinding Unit Project May 2015 – Feb 2016
9 Mangalam Cement, Morak, Rajasthan Grinding Unit Project May 2014 – Jul 2014
10 Maruti Cement Ltd., Siraha, Nepal Complete Plant Project including Crusher, Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Packing Plant Mar 2013 – Jan 2015
11 Subhashree Agni Cement, Nepal Complete Plant Project except Crusher including Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Packing Plant 2015 – 2016
12 Ultratech Cement Ltd., Vikram Cement Works, Neemuch, MP Conversion of Cement Mill Line III ESP to Baghouse 2016
13 Nuvoco Vistas, Jojobera, Jharkhand Installation of Clinker Slag Roller Press Circuit, Bucket Elevator and Belt Conveyor System 2018
14 EOM Engineering, Sonadih, Chhattisgarh Expansion of Packing Plant 2018
15 Subhashree Agni Cement, Nepal Complete Project of Cement Grinding Unit 2018
16 Ultratech Cement Ltd., Shambhupura, Rajasthan Fabrication and Erection of Belt Conveyor and Calciner Modification Work 2019
17 Ultratech Cement, Kotputli, Rajasthan Raw Mill Cyclone Modification and Height Increase of Cyclone 2018
18 J K Cement, Mangrol, Rajasthan Fabrication of Casing, Gas Ducts and Hopper of AQC Boiler and PH Boilers 2019
19 ACC Gagal, Barmana, Himachal Pradesh under Sinoma LNVT Fabrication and Erection of Fly Ash Dryer, Conveyor and Associated Equipment 2019 – 2020
20 Ambuja Cement, Marwar Mundwa, Rajasthan under Sinoma LNVT Fabrication, Copper Slag Blasting and Painting Works (1600 MT) 2019 – 2020
21 Sagar Cement Group – Satguru Cement Plant, Manawar, MP Fabrication and Erection of Raw Mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill and Complete Plant Equipment. Also executed WHRS Boiler Erection.

Fabrication: 6600 MT | Erection: 14500 MT
2020 – 2021
22 Ultratech Cement Ltd., Dhar, Madhya Pradesh – Line II Post Clinkerisation Project Fabrication and Erection of Post Clinkerisation Unit.

Fabrication: 4100 MT | Erection: 7900 MT
2021 – 2022
23 ACC Cement, Gagal, Himachal Pradesh Erection of Clinker Silo (Clinker Tank).

Erection: 575 MT
2021
24 JK Cement Group – Jaykaycem (Central) Ltd., Panna, MP Fabrication and Erection of Crusher.

Fabrication: 2100 MT | Erection: 4500 MT
2022
25 Ultratech Neem Ka Thana Cement Works, Rajasthan Fabrication and Erection of Post Clinkerisation Unit 2022
26 Ultratech Cement Ltd., Rajpura Cement Works, Punjab Fabrication and Erection of Complete Grinding Unit.

Fabrication: 4400 MT | Erection: 8900 MT
2023 – 2024
27 Ultratech Cement Ltd., Kotputli Cement Works, Rajasthan Fabrication and Erection of Post Clinkerisation Unit.

Fabrication: 3400 MT | Erection: 7600 MT
2023 – 2024
28 Shree Cement Ltd., Etah Grinding Unit, Uttar Pradesh Successfully completed Fabrication, Erection, Installation and Commissioning within benchmark timelines and received appreciation from Shree Cement Management. 2024 – 2025
29 Ultratech Cement Ltd., Dalla Cement Works, Uttar Pradesh Complete Pyro Upgradation Shutdown Project involving Fabrication, Dismantling and Erection of Preheater, Coal Mill and Associated Equipment executed successfully within just 40 days, setting a benchmark in the cement industry. 2025
30 Multiple Cement Plants Across India & Nepal Successful execution of modernization, expansion, shutdown, grinding unit, WHRS and clinkerisation projects across major cement manufacturing facilities. Ongoing Legacy