Completed Projects

  • Home
  • Completed Projects

With India’s infrastructure sector driving higher cement demand, the country is now the
second-largest global producer of quality cement. In response, industry participation is
expanding. The Planning Commission of India’s ‘Working Group on Cement Industry’ aims
to improve sector efficiency. At Sumit Engineering, we specialize in modernization,
maintenance, and technological upgrades. With our licenses for the erection of Boilers and
Waste Heat Recovery Systems (WHRS), we are equipped to help you optimize operations
and capitalize on growth opportunities.

Sr. No.Cement Plant                       Job DetailsTime period
1Zuari Cement Ltd., Yerraguntla, AP.Installed Fly ash Dryer and Baghouse Sep 2009 – May 2010
2JSW Cement Ltd., Nandyal.Fabrication and Erection of PreheaterApril 2010 – Feb 2011
3Zuari Cement Ltd., Attipattu.Fabrication and Erection of Grinding Unit (Cement Mill, Wagon tippler, Clinker Silo, Fly ash, Packing Plant, etc.) 3600TPDSep 2010 – August 2011
4Zuari Cement Ltd., Yerraguntla, AP.Installed Wagon loading system, Packing Plant, Coal mill shed, ESP, etc. Jan 2011 – Dec 2011
5Bagalkot Cement, Bagalkot, KA.Fabrication and Erection of Crusher, Baghouse, Preheater, fly ash silo, etc. July 2011 – Sep 2012
6Ultratech Cement Ltd., Birla White, Katni, MPMechanical Fabrication and Erection Job2014
7Zuari Cement, Solapur, MHFabrication and Erection of Complete project of Grinding unit of 3600TPD. Feb 2014 – Jan 2015
8Zuari Cement, Cochin, KeralaFabrication and Erection of Complete project of Grinding unit.May 2015 – Feb 2016
10Mangalam Cement, Morak, RajasthanGrinding Unit May 2014 – July 2014
11Maruti Cement Ltd., Siraha, Nepal.Complete Plant project ( Fabrication and Erection of Crusher, Raw mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill, Packing Plant, all equipments, etc.) March 2013 – Jan 2015
12Subhashree Agni Cement, Nepal.Complete Plant project except crusher ( Fabrication and Erection of Raw mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill, Packing Plant, all equipments, etc.) 2015-2016
13Ultratech Cement Ltd., Vikram Cement Works, Neemuch, MP.Job of Conversing Cement Mill Line III ESP to Baghouse.2016
14Nuvaco Vistas, Jojobera, Jharkhand.Project of installing clinker slag roller press circuit and Erection of Bucket elevator and belt Conveyor System.2018
15EOM Engineering, Sonadih, CG.Expansion of Packing Plant2018
16Subhashree Agni Cement, Nepal.Complete Project of Cement Grinding Unit.2018
17Ultratech Cement Ltd, Shambhupura, RajasthanFabrication and Erection of Belt Conveyor and Calciner Modification work.2019
18Ultratech Cement, Kotputli, Rajasthan Raw mill cyclone modification and Increased the height of Cyclone.2018
19J K Cement, Mangrol, Rajasthan.Fabrication of Casing, Gas ducts and hopper of AQC Boiler and PH Boilers. 2019
20ACC Gagal, Barmana, HP under Sinoma LNVTFabrication and Erection of Fly ash Dryer, Conveyor, etc.2019-20
21Ambuja Cement, Marwar, Mundwa, Rajasthan under Sinoma LNVTFabrication, Copper slag blasting & Painting of 16002019-2020
22Sagar Cement Group
Satguru Cement Plant, Jeerabad, Manawar, MP
Fabrication and Erection of Raw mill, Baghouse, Preheater, Kiln, ESP, Clinker Silo, Cement Mill, all equipments, etc. and Erection of WHRS boilers.
Fabrication = 6600 and Erection = 14500
2020-2021
23Ultratech Cement Limited, Dhar, Madhya Pradesh. Line II: Post Clinkerization Project.Fabrication and Erection of Post Clinkersation unit of UTCL Dhar Cement works.
Fabrication = 4100 and Erection = 7900 
2021-2022
24ACC Cement, Gagal, Himachal Pradesh. Erection of Clinker Silo (Clinker Tank)
Erection = 575
2021
25JK Cement Group
Jaykaycem (Central) Ltd., Panna, Madhya Pradesh 
Fabrication and Erection of Crusher.
Fabrication = 2100
Erection = 4500MT
2022
26Ultratech Neem Ka thana Cement Works, Sirohi, Neem Ka Thana,
Rajasthan
Fabrication and Erection of Post Clinkersation unit of UTCL Neem ka thana Cement works.2022
27Ultratech Cement Limited,
Rajpura Cement Works, Punjab 
Fabrication and Erection of Complete Grinding unit of UTCL Rajpura Cement works.
Fabrication = 4400 and Erection = 8900 
2023-2024
28Ultratech Cement Limited,
Kotputli Cement Works, Rajasthan 
Fabrication and Erection of Post Clinkerisation of UTCL Kotpulti Cement works.
Fabrication = 3400 and Erection = 7600  
2023-2024
29Shree Cement Limited,
Etah, Agra, Uttar Pradesh

Completed fabrication, erection, installation, and commissioning of Shree Cement Etah Grinding Unit within benchmark time, earning appreciation from the Shree Cement Management Team.

2024-2025
30Ultratech Cement Limited, Dalla Cement Works, Uttar PradeshComplete Pyro Upgradation Shutdown Project (involving Fabrication,
Dismantling & Erection of preheater, coal mill, etc) was successfully executed within just a
span of 40 days. Setting up the benchmark in cement industry.
2025